Home
News
Contacts / addresses

Trust Policies

Situations vacant
Development manager's report
Canal history
CCS 1976 - 1997
Restoration
1997-2006 summary
CC Partnership
Chairman's message
Voluntary
restoration project
Canal resources
& postal sales
Along the towpath
The way we were
Maps

Supporters' meetings

Volunteer timesheet

Health and safety

Forthcoming events

The Chesterfield Canal - Volunteer Restoration Project

The Trust's volunteer restoration working party is working every Sunday in early 2007 around Mill Green Bridge at Staveley (behind Morrison's supermarket). If you would be interested in joining them just turn up on site for an introduction or contact Mick Hodgetts on 01246 620695.

VOLUNTEER RESTORATION PROJECT

Volunteer vacancies (visit page)

December 7th 2007

VOLUNTARY RESTORATION UPDATE

Mill Green Restoration project latest

The completed section at Mill Green Staveley
The completed section at Mill Green Staveley

As we are now well into our second year of works on the south side of Mill Green Bridge were a section of canal walling had become unstable and eventually collapsed into the canal works have now almost being completed.

Looking back to June 2006 Contactors installed a dam to seal of the canal; we installed Stop planks at the other end near the bridge so the water could be then pumped out. Once an empty channel was achieved it was obvious that instead of a repair to a section and patching up as necessary a complete rebuild was required to around 50 meters of walling on the towing path side and up to 8 meters on the offside.

Works have proceeded over last year and the trust can really be proud of commitment the volunteers have shown with regulars turning up week in week out plus a few new faces for good measures. The method specification has been the same as we have undertaken on the other side of the Bridge with 1.2 meter concrete walling built on 200mm concrete foundation then backfilled with concrete all mixed on site to provide walling 500mm to just below water level. The finish above is of 350mm of stone to provide a natural traditional finish.

We were then at a stage this July when the cut of dams were removed and the detailed finishing works including towpath reinstatement, resetting of the stop plank holder & bench, mooring bollard setting and an area that will provide for two disabled fishing pegs has been constructed.

At this point our works will cease in Staveley until the program of works on the canal due to commence in 2008 by the highway engineers has been drawn up. It is hoped that we will be able to continue with the necessary bank raising that will take the Original Canal into the diverted section.

Over the last few weeks the trust volunteers has been assisting DCC Countryside Service carrying out repairs to some of the lock chambers and making preparations for some other works that will be undertaken by Rochdale Canal workshops early next year.

Winter works program

As works are well underway on the Phase 1 of the MEGZS/Canal scheme it has made it not possible as things stand at the moment for any volunteer works in the Mill Green - Hall Lane area to proceed in the short term.

It has therefore been decided to remove the vegetation in the canal south of the site that has been cleared by the Waterway Recovery Group at Renishaw. Since the unsuccessful re watering twelve years ago, this section has be left dry and become abundant with young trees and harsh vegetation.

This will be a change from the works we have been undertaking for many years but has they say a change ids as good has a rest. There is also some construction works repairing the overflow weir and some channel investigation to be carried out upstream to ascertain the correct profile of this section of canal to be restored.

The works are due to commence some time in October after all the works at Mill Green are finished. The site is situated at Renishaw Just of the A6135- Barbrough Road next to the Sitwell Arms. Any further enquiries please contact either Terry or Myself.

MICK HODGETTS


November 29th 2007

CCT Restoration Party volunteers with their Derbyshire Excellence in the Community Award

Top: CCT Restoration Party volunteers with their Derbyshire Excellence in the Community award. (Photo: Mick Hodgetts - click to enlarge.)


Stop planks being lowered into position at the bottom of Wheeldon Mill Lock.

Above and below: Stop planks being lowered into position at the bottom of Wheeldon Mill Lock. (Photo: Mick Hodgetts - click to enlarge.)

Stop planks being lowered into position at the bottom of Wheeldon Mill Lock.


November 4th 2007

Volunteers from the Chesterfield sub-aqua club assist CCT restoration working party by installing stop planks at Hollingwood Lock prior to pumping out the lock for work on the bottom gates.

Chesterfield sub-aqua club assist CCT restoration working party


Plaque for Andy Oxley

Andy Oxley (centre) from Killamarsh, who has completed ten years of voluntary work helping to restore the Chesterfield Canal, was presented with a plaque to honour his efforts on Sunday April 29th.

Andy is flanked by supervisor Mick Hodgetts (on Andy's right) and assistant supervisor Terry Berridge (left). Between them the trio have given more than fifty years of volunteer service to the canal's restoration!

Currently working on Sundays at Mill Green Staveley, the restoration group would welcome more volunteers. If you are interested contact Mick on 01246 620695.


The Canal Trust’s voluntary restoration project

Mill Green to Hall Lane - Staveley
By Mick Hodgetts

Background

Click to enlargeFollowing closure of the Derbyshire end of the canal in the early 20th century the sectional from Chesterfield to Renishaw was retained as a water supply for the Staveley & Renishaw Iron works. Recent photographs from the early 1960s show the canal still in good condition. In 1971 the iron works at Renishaw ceased their abstraction and discharging of canal water and by then the section of the canal maintained as a watercourse from Hollingwood Lock to near Spinkhill (aprox 4 miles) was in poor condition.

Staveley Puddle Bank was in great need of repair and could not maintain the canal at full operating capacity levels, resulting in stop planks being installed at Mill Green Bridge and the water being maintained at a lower level throughout this section as far as the narrows at Barlborough Rd (A616) Renishaw. Here a pumping Station was installed to transfer water over a stop plank dam to achieve the full canal depth towards Renishaw Iron Works. According to an early publication of Cuckoo it was decided by British Waterways Board that although infilling this section would not be any cheaper than to retain the canal as a remainder waterway for the next 10 - 15 years, infilling was the more favoured option and favoured by the relevant local authorities.

Condition of the Canal at Mill Green

By the mid-1980s the canal at Mill Green had become a local rubbish dump. No maintenance was undertaken below Hollingwood Lock and a concrete dam had been cast in the stop plank grooves next to Mill Green Bridge. The canal channel from here was filled in and for the first 100metres past Mill Green Bridge half the width of the canal onward had a further 10ft of overfilling from ajacent landscaping works following both the demolition of houses at Mill Green and further developments nearby.

The towpath originally at a level, dips then rises. It is hard to find the original location in some places and it is easy to assume that this is due to mining subsidence. However with careful observation on site you will find the offside bank is still at the original level. Therefore in some places the towing path embankment may have been bulldozed into the channel. In other areas the footpath has become established on the route of the canal leaving the towpath route to become overgrown.

The first phase of voluntary restoration

Click to enlargeWith the volunteer input to restoration of the Canal between Chesterfield and Mill Green completed by the year 2000, the Canal Trust has taken on the next major project at Mill Green, Staveley, on a voluntary basis. As the next major phase of restoration on a major scale is reliant on the outcome of future engineering and benefit studies, it was decided that the Trust pursue the continuing restoration to maintain our profile and show something happening on site.

The removal of the over-tipping and the building of the canal wash walls, well documented over past issues of Cuckoo, has taken 2-3 years to complete. This work was completed by September last year leaving just the canal channel itself to be dredged and requiring £40,000 to be raised to do it- the arisings were classed as toxic waste and had to be taken away to tip. Much credit is due to David Trickett and Martin Bloomfield who put together the funding package which raised this enormous amount allowing the canal dredging works to take place.

After what seemed a lifetime in preparation and waiting, the earthworks contractor J C Balls commenced on Wednesday 19th June. With all the pumping out undertaken previously leaving a fully dry site, the first 2-ton bucket full was extracted at 7.30am. As expected the first hour was the most difficult due to establishing between all parties where and what the clay bed of the canal was. All was quickly resolved and good progress made on the excavation of the bridge approach. Here for about fifteen metres the canal’s profile was of a simple flat clay bed between two vertical walls.

Beyond this the canal sides are battered, formed with clay more closely resembling the natural orange type found locally in the area. Both sides have wash walling constructed on top of this. By the end of the first day a good third of the excavation was complete. The following day was very productive with one massive 360-degree excavator and six 40-tonne lorries at work. I probed the canal bed as the works progressed.

The profile of the far bank beyond the retaining wall was formed from the natural clay strata; this has left a natural clay shelf below the water line that will in time provide an area for wildlife colonisation. The last fifteen metres was trimmed down deeper to form a boat turning point, as this will act (not for too long I hope) as the head of navigation. The canal bed was puddled blue clay with the towing path wash wall we had constructed on top of the clay batter up to one-metre lower the original construction.

Throughout the dredging operation the canal bed was carefully monitored to avoid digging into it. By Friday afternoon, excavation of the full 100metres was satisfactorily completed and a batter formed and compacted across the end. To avoid any drying out of the canal bed we immediately began to re-water this section by lifting the top stop plank in the narrows by Mill Green Bridge.

This became quite an event attended by Staveley Neighbourhood Management team, one of the project sponsors. Within three hours the section was full with not a leak in sight. That is how things stood for two weeks until the stop planks were removed by the contractors, with kind assistance from the sub aqua club.

The second phase of voluntary restoration

Click to enlargeAt the end of last September we moved our worksite a further 100 metres to Constitution Hill footpath crossing. We have now restored both sides of the bridge hole and are currently rebuilding the wash wall back towards Mill Green to eventually join up with the newly re-watered section.

With regard to rebuilding the footbridge, at this moment I do not feel that our small and dedicated band of volunteers could undertake this, although we would not rule out any involvement at some stage – watch this space. This is only the start of bigger things that should happen in the near future when the big guns again arrive back on site. We are only a small but dedicated group that intend to prove to everyone that there is a desire within the local community to see the canal restored and are willing to do our bit to see it achieved.

Our thanks go to those organisations and bodies who have contributed to the cost of the dredging:

Landfill Tax Credit Scheme:

Waste Recycling Environmental (WREN) and 
Viridor Credits - Derbyshire;

Third Party Funder:

Staveley Neighbourhood Management;

Grants from:

Staveley Town Council,
Staveley Miners' Welfare, 
Derbyshire Greenwatch,
Waterways Trust.


Tapton Lock
visitor centre

Public transport
Towpath walks
Forthcoming events
Angling
Wildlife
CCT magazine
'Cuckoo'
Tripboat cruises
Publicity & sales
Canalside pubs, restaurants and b&b
Canal & towpath
stoppages
Photo tours
IWA trail boat festival 2005 photos
Join us! (membership)
The New Dawn Project
Donations, Legacies and Bequests
Links
Email for the chairman
Guestbook

Constitution Hill Update

Click to enlargeWork on the site of the Constitution Hill Bridge commenced in September 2003. The canal is infilled at this point so the old wash walls were excavated and an examination made of their general condition. As a public footpath crosses the canal line at this point, this had to be diverted and the work site fenced.

The offside wall was found to be in a reasonable condition but the towing path side was in a very poor state. It was decided therefore to start on the offside, retaining as much of the original material as possible. Phillip Thurston checked the levels and found that the top of the wall needed raising by approximately half-a-metre. An entirely new wing wall has been added on the Hall Lane side, constructed from recycled kerbs kindly supplied by Derbyshire County Council Highways Department.

The offside was completed by the end of 2003 and this year work is concentrated on the towing path walls. As these were in poor condition, and the canal is sufficiently wide, it was decided to build a completely new wall in front of the old. Firstly the old wall was photographed by Terry Berridge who is keeping a full photographic record of the work as it progresses. By May, this wall was completed and the final layer of coping stones added. The canal through the bridge hole has been temporarily filled back in for health and safety reasons.

During the excavation of the towing path side, the remains of the old wash walls were uncovered and it is hoped to restore these back the one-hundred-or-so yards towards Mill Green to join up with that of the recently re-watered section. The re-watering of the Constitution Hill section will be part of the MEGZ road scheme and it is hoped that the replacement of the Constitution Hill footbridge can also be included in this project.

Martin Bloomfield.

Volunteer restoration project progress in photos – May 2004

Click to enlarge
Click to enlarge
Volunteers ( l to r)Andy Oxley Terry Berridge Arnie Chapman beside the section at Mill Green Staveley that was rewatered on May 21st
Photo taken 23 May, 2004
photo ©
Andy Oxley cutting coping
stones at Mill Green
Photo taken 23 May, 2004
photo ©
Click to enlarge
Click to enlarge
(l to r) Arnie Chapman Mick Cook and Terry Berridge position
a coper at Mill Green
Photo taken 23 May, 2004
photo ©
A busy scene on the canal at Mill Green Staveley 23.05.04
CCT refreshment caravan and walkers enjoying the towing path
Photo taken 23 May, 2004
photo ©
Click to enlarge
Click to enlarge
(l to r) CCT volunteers Linda Thorpe Ron Stanley and Janice Stanley provide refreshments at Mill Green Staveley every Sunday for the working party and walkers on the canal towpath
and Trans Pennine Trail
Photo taken 23 May, 2004
photo ©
The new car park for canal visitors
at Mill Green Staveley
Photo taken 23 May, 2004
photo ©

Volunteer restoration project progress – February 2004

Work site - Mill Green, Staveley (near Morrison’s supermarket)

Working day - Most Sundays 9-30 am – 5 pm

Wednesday Evenings, May – September 7pm-9 30 pm

(Please check for confirmation if not a regular participant)

The Chesterfield Canal Trust volunteer working party is currently working on the section of canal beyond the limit of navigation at Mill Green, Staveley as far as Hall Lane.

This project will hopefully pave the way forward for future restoration of the Chesterfield Canal towards Killamarsh.

The first 100metres near Mill Green Bridge has seen extensive works over recent years with over 500 tons of overfilling being removed from the line of the canal, new canalside walling with realigned towing path, landscaping & mooring bollards.

The canal in this area when re-watered will provide an amenity for Staveley Town Centre with visitor moorings for boats, additional fishing and a restored towpath for walkers, cyclist and the disabled.

We are now attempting to raise £40,000+ to excavate the infill from the channel and remove it from site due to an area of contaminated material near Mill Green Bridge.

Works have now moved on downstream 100metres to an area where a footbridge carrying a public footpath from Staveley Church to Barrow Hill (historically known as Constitutional Hill) crossed over the canal. This was removed over 30 years ago and resulted in the footpath crossing the canal infill. The offside canal channel wall has been restored and raised to accommodate the finished operating water level.

Works are now proceeding on the towpath-side wall which will eventually tie in with the 100-metre section completed last year.

Anyone who wishes to participate on any of the above activities please contact the organisers below

Works program co-ordinator Mick Hodgetts Tel 01246 620695

Volunteer co-ordinator Terry Berridge Tel 01246 273055


Volunteer restoration project progress – September 2003

Staveley

Work site - Mill Green, Staveley (4 miles from Chesterfield Behind Morrison’s superstore.

Working day - Every Sunday 9-30 am – 5 pm

At long last the construction works near Mill Green Bridge are complete with realigned towing path, landscaping & mooring bollards. The canal in this area when re watered will provide an amenity for Staveley Town centre with visitor moorings for boats, more fishing area and restored towpath for walkers, cyclist and the disabled.

Works have proceeded well throughout the summer aided by a small increase in volunteer numbers. Together with the clay donated by Fitzwize for back filling, we were able to find a supply within the canal infill itself. This will require storing somewhere nearby so it can be used for future engineering works on the canal.

Mill Green: Volunteers from the Trust's workparty putting the finishing touches to the towpath.
Mill Green: Completed canal wall and towpath - Funding is being saught to remove the spoil from the channel (right)

 

On behalf of the Canal trust I would like to thank all concerned for their kind assistance & generosity for this project.

We are now attempting to raise the massive £40,000+ to remove the infill from the channel and remove it from site due to one area of low rate contamination near the bridge.

Works have now moved on downstream 100metres to an area where a footbridge carrying a public footpath from Staveley Church to Barrow Hill (historically known as Constitution Hill) crossed over the canal.

The bridge was removed over 30 years ago and resulted in the footpath crossing the canal at ground level. Much of the canal structure still exists here together with the foundations of the old footbridge.


Constitution Hill: Oct27, excavations to find the original footbridge foundations. Rebuilding the canal walls has commenced.
Rother Clearance: Strimming the river banks in Chesterfield.

 

RIVER ROTHER SECTION

River Rother/Chesterfield Canal next to Arnold Lavers, Tapton

Wednesday Evenings May – September 7pm – 9-30pm

Following the enormous amount of work that was undertaken on the WRG North West weekend last January, we have spent eight evenings this summer carrying out vegetation control & striming. We aim to continue this work next summer and keep this section of the waterway open as an amenity that will hopefully serve an adjacent canal terminus in the future on adjacent currently derelict land.

The vegetation in this area is abundant and investment is required for complete removal within a full program of restoration. To leave it alone cannot be seen as a way forward. Year after year trees are growing through the stone-walling of the river bank and sections crumble into the water. This is a man made canalised river and should be maintained accordingly.

Anyone who wishes to participate in any of the above activities please contact the organisers below

Works Program Co-ordinator Mick Hodgetts Tel 01246 620695
Volunteer Co-ordinator Terry Berridge Tel 01246 273055


 

all content © Chesterfield Canal Trust :: site management by David